Please click here to download the Maintenance of Traffic (MOT) Plan for the following phases.

 

Phase 1 and Phase 2 – 01/27/2020 – 03/06/2020:

Knights Run Eastbound

Crews will begin work on eastbound Knights Run as part of the Harbour Island Force Main Replacement Design Build Project. This initial phase is designed to relocate the force main off Harbour Island. During this phase, crews will be installing the piping to capture the wastewater from the lift station on the island in order to reconnect it to the planned construction of a new force main located off the Island. There are no plans to close Knights Run as crews will shift the traffic to allow for one lane travel in each direction.

 

Phase 3 – 03/16/2020 – 04/18/2020:

Detour at Southbound Beneficial Bridge Closure Daily 9:00AM to 4:00PM of all southbound lanes. After 4:00PM, one southbound lane will be open. This work is to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

 

Phase 3 – 03/16/2020 – 04/10/2020:

Beneficial Drive from Knights Run to Harbour Place Drive 9:00AM to 4:00PM, each night traffic is down to a one lane detour. This work is to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

 

Phase 3 – 04/13/2020 – 04/18/2020:

Beneficial Drive at Harbour Place Drive Intersection 9:00AM to 4:00PM for crossing detour daily. Each night open to one lane. This work is to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

 

Phase 4 – 04/13/2020 – 05/01/2020:

Beneficial Drive Daily closure for North of Harbour Place Drive. This work is to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

 

Phase 4 – 05/04/2020 – 05/22/2020:

Beneficial Drive lane closure for directional drilling to allow for directional drilling boring bit. Southbound Beneficial down to one lane. This work is to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

 

Phase 5 – 05/22/2020 – 06/12/2020:

Restoration work to be completed by June 12

Beneficial Drive approach and bridge lane closure to one lane to allow for restoration of area at each pit location. This will complete the work to relocate the force main off Harbour Island and reconnect it to the planned construction of a new force main located off the Island.

Updated: November 8, 2019

From December 2 to December 17, 2019, the intersection at Franklin and Old Water St will remain closed during this time while crews complete and finish testing the 48″ force main located east of Franklin.

 

Updated: October 25, 2019

Between Thanksgiving and Christmas 2019, crews will finish paving and striping on Old Water Street from Morgan Street to Franklin Street.

 

The City of Tampa recommends that motorists use alternate routes to avoid traffic congestion.

Harbour Island October 2019 Upcoming Franklin Closure-Maintenance of Traffic Plan

Download and view the Maintenance of Traffic (MOT) Plan.

Updated: October 2, 2018

 

A portion of S Franklin Street between E Brorein Street and Channelside Drive and S Tampa Street between E Brorein Street and S Franklin Street will close beginning on Sunday, October 7, 2018 for utility construction. Both southbound lanes on S Franklin Street between E Brorein Street and Channelside Drive and S Tampa Street between E Brorein Street and S Franklin Street will close at 12:01 am on October 7, 2018.

 

Contractors will be working in the southbound lanes on S Franklin Street between E Brorein Street and Channelside Drive requiring S Tampa Street between E Brorein Street and S Franklin Street to be closed during construction. The City contractor will be doing emergency repair work on an existing sewer force main and a private contractor will be installing utilities for a new restaurant at the Tampa Convention Center in the southbound lanes on S Franklin Street between E Brorein Street and Channelside Drive.

 

The sidewalk on the west side of S Franklin Street between E Brorein Street and Channelside Drive will be closed during construction. Pedestrians will be detoured to other available sidewalks with signage.

 

It is anticipated that all lanes on S Franklin Street and S Tampa Street will reopen to traffic by 4 pm on Thursday, October 11, 2018, weather permitting.

 